Trimmed

I have completed the chair rail molding as well as the trim around the doorway, closet and electrical panel. All nails have been patched and painted over. The ceiling will be installed next.

Saturday, March 20, 2010

Paintin' The Blues

Two coats of paint have been applied and the room is starting to take shape. I used the same color blue that was used in the other two rooms. The addition of chair rail molding along with trim work around the doorways and electrical panel is next.



Saturday, March 13, 2010

Primed And Ready

Ready for paint that is! The mud and tape has been completed. The walls were sanded to make everything smooth and then the primer was applied. The next step is to get some color on the walls.



Sunday, March 7, 2010

Drywall

I finished the wiring and put up the drywall. I am doing 1/2 sheets due to the difficulty of carrying a full sheet of drywall down my tight stairway. I'll cover the seam with chair rail molding just like in the other rooms. Mud and tape is next then on to the primer!



Monday, March 1, 2010

We've Been Framed!

Well not really but the walls have been! All the studs are up and the insulation is in place on the exterior wall. Some of the wiring has also been installed. Once the wiring is complete, the drywall will be put up next.